When this checklist applies
-
The 7-step cost checklist
-
Step 1: Compare on the working-radius load curve, not headline capacity
-
Step 2: Pull freight, offloading, and last-mile out of the "included" bucket
-
Step 3: Reconcile foundation, anchoring, and tie-in costs between two parties
-
Step 4: Pull a 3-year spares price list and model the annual wear cost
-
Step 5: Price install, climbing, and dismantle as a separate line
-
Step 6: Run an exit-cost model before you commit
-
Step 7: Force every "not mentioned" fee onto one page
-
Step 1: Compare on the working-radius load curve, not headline capacity
-
Watch-outs and common mistakes
I'm the procurement manager at a 220-person construction company. Over seven years I've pushed about $1.8M of lifting equipment budget through our TCO spreadsheet — mostly mid-to-large tower cranes from Potain, Liebherr, and Saez. The first two years cost me two expensive lessons on "low quote, high hidden cost" deals. The checklist below is what we settled on afterwards. The first version had eleven items. Or rather, it had eleven items on paper and two items I actually used. The seven below are what survived.
If you searched for how to make an origami crane, wrong page. This is about six-figure tower cranes. Everything below assumes you're comparing new-machine quotes or scrolling through a Potain crane for sale listing — not renting one for six weeks.
When this checklist applies
Use it when you're buying a tower crane, or seriously evaluating one for purchase — self-erecting, flat-top, or luffing; new or used. It also works for replacement decisions, when you're deciding whether to swap an aging machine instead of repairing it again.
Don't use it for rentals. Rentals are a service-response game. Buying is a total-cost-of-ownership game. Different math, different checklist.
What this actually solves: it stops you from picking the cheapest quote that then costs 15–20% more over five years in freight, foundation, spares, climbing, and commissioning. All the costs that don't show up until you've signed.
The 7-step cost checklist
Step 1: Compare on the working-radius load curve, not headline capacity
Every quote leads with maximum capacity. But maximum capacity is measured at a specific radius that rarely matches your site plan. On a project I'm running now, we needed 2.4t at 45m radius with 60m hook height. A competitor's "8-ton" crane couldn't do 2.4t at 45m — its curve dropped below that at 38m. Their quote came in lower than the Potain MD 569 we ended up shortlisting. It was the wrong crane for the work, and we nearly missed it because the capacity numbers were on different axes.
Checkpoint: Before you compare prices, write one line: "I need ___ tons at ___ meters radius, at ___ meters hook height." Send that to every vendor. Ask for the corresponding number in writing. If a vendor can't answer in writing, that's your first red flag — and probably your last one for that vendor.
Step 2: Pull freight, offloading, and last-mile out of the "included" bucket
Even a quote that says "freight included" usually means plant-to-port or plant-to-yard. Actual door-to-foundation cost includes last-mile transport, offloading equipment, road permits or width restrictions, and possibly a temporary repositioning move if your site has two build phases.
In a 2023 deal we got hit with a $2,800 last-mile surcharge because the site access road couldn't take the trailer without an escort truck. The quote did include freight. It just didn't include that freight.
Checkpoint: Ask for a "door-to-foundation" quote, not a freight line item. Have the vendor confirm the access route matches your actual site — width, soil bearing, overhead lines. If they haven't seen the access route, they're guessing, and you're paying for their guess.
Step 3: Reconcile foundation, anchoring, and tie-in costs between two parties
This is usually the biggest missed cost — mainly because the civil contractor and the crane vendor each assume the other is pricing it. One side quotes the rebar and concrete. The other assumes the embedded anchor frame is coming from them. Nobody quotes the anchor frame. It shows up on site as a change order.
Checkpoint: Make a three-column table: foundation concrete, embedded parts (anchor frame, bolts, embedded sections), and tie rods / wall ties. Put the vendor's standard embedded-part list on one side, the civil contractor's quote on the other, and reconcile line by line. Ask both parties to sign the reconciliation before the contract. Anything missing on one side is an add-on later.
Step 4: Pull a 3-year spares price list and model the annual wear cost
Spare parts are where brands actually differ in long-run cost. Potain's parts network is broad and price lists are published, which makes this easier to price than most — but even with a strong network, individual part prices can vary 40% between catalog generation and dealer pricing on discontinued items.
Get a written 3-year price list for wear items: hoist rope, brake linings, limit switches, slew gear seals, and any proprietary electronics. Then ask: for anything on this list that may go out of catalog in five years, what's the designated replacement part number, and is it priced the same? A blank stare here is worth 3–6% of the purchase price over five years.
Checkpoint: Model 5-year spares cost per machine. For a mid-size tower crane, wear parts typically land at 3–6% of the machine price over five years. That's enough to flip which quote "wins."
Step 5: Price install, climbing, and dismantle as a separate line
Every telescoping climb up a shaft or tie-in is billed separately by the vendor or service team. It's never in the purchase price. On a building with twelve floors of climbing, you're looking at four to six climbs. On a project that rushes or stalls, it's eight or more — and each one is a line item.
Checkpoint: Ask the vendor to quote four things separately: initial install, each climb, final dismantle, and a written clause for "delayed climb surcharge." That last clause is the one that bites. If your site isn't ready on the planned climb date, a $2,000/day idle charge can show up without warning. Get the number before you sign, not after.
Total install + climbing + dismantle is typically 6–12% of the machine price. If it's not on the comparison sheet, you're not comparing the same thing.
Step 6: Run an exit-cost model before you commit
Tower cranes hold value, but not equally. Large-capacity or unusual models have a thinner buyer pool — you can list for six months and get lowball offers. Standard mid-size models move faster. The purchase is only half the equation; the other half is what you recover when you sell.
Checkpoint: Run the model: purchase price − 5-year residual − 5-year major service cost. Then pull three local brokers' used listings for the same model. If there are no used listings in your region within the last twelve months, assume 15–25% lower residual than whatever the broker tells you. Thin markets discount hard.
Step 7: Force every "not mentioned" fee onto one page
Even after Steps 1–6, some vendors leave items off the quote: commissioning, operator training, acceptance support with the local safety authority, and certification fees. None of these are optional in practice. They just don't show up until after the down payment.
Checkpoint: Build a one-page table. Columns: Scope / Vendor quote says included / Vendor confirms in writing. Anything left blank gets treated as not included, and priced at the industry average for comparison. Ask directly: "Is training included? Is commissioning included? Is the first load test included?" If the answer is "I'll check with our service team," treat it as a no.
Watch-outs and common mistakes
Don't let "more expensive equals more professional" take over. The quality-perception argument is real, but smaller than the sales pitch suggests. What clients and site inspectors actually notice is whether the crane is clean, quiet, on schedule, and run by an operator who doesn't shake the load. A well-kept mid-size machine with a good operator beats a premium machine that's been sitting dirty next to a bad access road. Buy the right machine for the work, not the flagship model.
Time pressure changes the process — but not Step 1. If a tender closes in 48 hours, do Step 1 for every quote and price the rest at regional averages. Don't skip Step 1. It's the only step that actually changes which quote is right. Everything else is negotiable after the fact. I learned that one the hard way in mid-2024, when I signed a machine that was technically "8 tons" but functionally wrong at our working radius.
Used-listing traps. A Potain crane for sale listing at 20% below market usually isn't. It's either been dismantled twice, or it has a repair history the seller won't disclose. Ask for the maintenance log, the last annual inspection, and the last rope and brake change. If any of those is missing, price in 5–10% of the purchase price for unknowns. If all three are missing, walk.
Time-sensitive pricing. The foundation and tie-in pricing referenced here reflects what we saw in Q4 2024. Steel and transport costs move, so re-quote before finalizing your 2025 budget.
Run the checklist once and you'll see it takes about a day of real work — mostly asking for things in writing, then reading the fine print. The alternative is finding out eighteen months in.